Day 8


The steel frame for the main front Cathedral window is now in place. After some difficulty because some of the blockwork in the foundations had to be broken out. The steel frame work had been made to fit straight on to the concrete and we had been informed otherwise. Any way all is now well and it was lowered in to place with great easy - adjusted to fit and now we can see the front of the house taking shape.
Yesterday was spent getting the rafters finished and the roof ready for boarding.
This evening they have infact boarded the back roof which is now almost ready for tiling.